Share |

Content about ARCO

November 19, 2012

SAN DIEGO — Textile rental company turns to ARCO/Murray National Construction Co. after boiler malfunction

SAN DIEGO — ARCO/Murray National Construction Co. completed a mechanical room relocation and canopy building addition here for Alsco earlier this year.

Last November, a boiler malfunction caused the textile rental company to shut down its mechanical room and rent a temporary boiler. Alsco hired ARCO/Murray to relocate the mechanical room and install new mechanical-room equipment. The firm was able to complete the project by early April, limiting the amount of money spent to utilize a temporary boiler.

The mechanical-room relocation included demolition of a two-story storage and office area to make room for the new system, which included a 400-horsepower boiler, a water softener package, and a brand-new water system with a stack economizer. ADA-compliant bathrooms were also constructed.

ARCO/Murray was responsible for the demolition and reconstruction as well as all power and process piping tie-ins to the equipment within the mechanical room and out to the existing wash floor and wastewater systems.

While the expedited mechanical-room project was under construction, ARCO/Murray was also hired to design and permit a 5,000-square-foot loading dock addition. Through careful coordination with the City of San Diego and Alsco, ARCO/Murray was able to complete the project with limited interruption of Alsco’s operations and minor disruption of the city’s traffic flow, the company reports.

Along with the canopy, ARCO/Murray was responsible for demolishing and replacing approximately 300 linear feet of sidewalk. The new dock canopy is able to hold six step vans and one box truck, increasing loading capacity and allowing Alsco to load completely within its property lines.

Project executive Elliot Mata and project manager Patrick Hidder represented ARCO/Murray. Bob Stephens served as Alsco’s corporate engineer, and Shane Harrison, the San Diego plant’s general manager, served a vital role in coordinating between Alsco and ARCO/Murray during construction.

December 14, 2011

DUBOIS, Pa. — ARCO/Murray National Construction Co. reports that it recently completed a facility expansion and equipment installation project for Paris Companies, a regional textile services company servicing the uniform and healthcare markets and led by CEO David Stern.

The project consisted of three expansions, totaling 14,000 square feet, to the DuBois healthcare facility originally built in 2008. Work included a new soil-dock expansion (tailored to Paris’ custom twin-level “super” trailers), finishing-area addition (creating more folding capacity, supplemented by installation of another ironer line), and wash-floor expansion (creating room for a new tunnel washer and dryers, plus additional soil storage rail).

Construction was completed while the plant was operating three shifts, six days a week, and Paris’ quota of 900,000 pounds per week was not affected, ARCO/Murray says. Paris had converted to three shifts earlier this year to cover increased volume. With the third tunnel washer operational in October, the plant was able to return to two shifts.

ARCO/Murray attributes the project’s successful completion to close coordination with Tom Walsh, Paris Cos. director of engineering, and CJ Spencer, the plant’s general manager.

Representing ARCO/Murray were Elliot Mata, project executive, and Anthony Lovero, project manager. The new wash equipment was procured through Frank Constable and distributor PAC Industries, and the material-handling portion was done with Jensen Futurail represented by Simon Nield.

October 15, 2010

SALT LAKE CITY — G&K Services recently expanded its facility here on the northwest side, adding 10,000 square feet of plant space, a 5,000-square-foot office build-out, and an acre of site expansion, according to ARCO/Murray National Construction Co.’s Laundry Division, Oakbrook Terrace, Ill., which oversaw the project.

The roof structure of the plant addition was designed to carry the load of overhead conveyance systems.